CURRENT STATUS : -

1) M.C.G.M has agreed to grant the lease and clear the file and
     formalities Lease are under process which are likely to be
     completed in 1 months time after which work will commence on site

 

2) Proposal is delayed due to lease renewal procedure from BMC Estate

     Department and which is expected shortly.

 

3) Piling work is in progress but due to went-of 750MM DIA piling

     machine work is temporary on Hold

OLD STATUS : -

1.  MHADA NOC received.

2.  C.F.O NOC received.

3.  D.P. NOC  received.

5.  E.E.T.& C. NOC received.
6.  Adjoining NOC expected shortly.
7.  Municipal Architects NOC Received.
8.  A.O.(Estates) NOC & IDO expected shortly thereafter work will     

    commence. 

9. Estates N.O.C Received.

10. IOD Expected Shortly.

11. I.O.D Received

12. Approved Plans Received

13. Shor Piling work started on site

14. Tree NOC Received

15. S.P&S.W.D NOC Received
16. Drainage Approval Awaited
17. H.E NOC Received
18. Revised C.F.O Awaited
19. Revised Est.NOC for C.C Expected Shortly

20.Work will commence shortly

21. NO Dues NOC Received

Note:Due to amalgamation of adjoining property plans had to be 

                  revised which are under final scrutiny for the approval. And are

              expected in forth night time after which work will commence.