Payment Schedule |
|
|
|
|
|
|
WORK |
1 BHK |
2 BHK |
3BHK |
|
Demolition |
189000 |
357000 |
405000 |
|
Footing |
65000 |
119000 |
135000 |
|
Plinth Work |
134000 |
238000 |
270000 |
|
1st Podium Slab |
65000 |
119000 |
135000 |
|
2nd Podium Slab |
65000 |
119000 |
135000 |
|
1st Slab |
65000 |
119000 |
135000 |
|
2nd Slab |
65000 |
119000 |
135000 |
|
3rd Slab |
65000 |
119000 |
135000 |
|
4th Slab |
65000 |
119000 |
135000 |
|
5th Slab |
65000 |
119000 |
135000 |
|
6th Slab |
65000 |
119000 |
135000 |
|
7th Slab |
65000 |
119000 |
135000 |
|
8th Slab |
65000 |
119000 |
135000 |
|
9th Slab |
65000 |
119000 |
135000 |
|
10th Slab |
65000 |
119000 |
135000 |
|
11th Slab |
65000 |
119000 |
135000 |
|
12th Slab |
65000 |
119000 |
135000 |
|
13th Slab |
65000 |
119000 |
135000 |
|
14th Slab |
65000 |
119000 |
135000 |
|
Terrace Slab |
65000 |
119000 |
135000 |
|
Brick Work |
132000 |
238000 |
270000 |
|
Plaster Work |
260000 |
476000 |
540000 |
|
Flooring & Fixing Door Work |
260000 |
476000 |
540000 |
|
Plumbing & Sanitary Work |
260000 |
476000 |
540000 |
|
Finishing Work |
67000 |
119000 |
135000 |
|
On or Before Possession |
65000 |
119000 |
135000 |
|
TOTAL |
2537000 |
4641000 |
5265000 |
|
|
|

|
 |